Razorback Oil - Field Trial Results   >>


 |  Razorback Production - Fine #1  | Razorback Production - Nole #1  | 

 |  Cyclic Microbial Injection  |  MEOR/MIOR Field Flood  | 



Razorback Production began MEOR treatments on its Nole #1 in 1988.
TREATMENT METHOD:  

One (1) - 15 gallon injection of Wel-Prep 5 in March 7, 1988.  The well was shut-in for 5 days
and then circulated for an additional 24 hours.  Gas pressure began to rise after the first 48 hours.
A 150 PSI pop-off valve began venting every 15 to 30 minutes by the 4th day.   Well was turned
into production on March 13, 1988. 

   Immediate Pre-Treatment               Post-Treatment

    Oil:   6 bbl/day                        	10 bbl/day
    API Gravity: 24.2o                 	API Gravity: 30.0o
    Gas Pressure:  80 PSI                       150+ PSI

According to the producer, gas pressure increased on the Nole #1 within 48 hours following
treatment.  The Noll #1 was turned back into production after a 5 day shut-in and one day's
circulation.  It was pumped continuously (24 hours a day) with no pump cycle set.   As of
1 April 1988 oil production was holding at 10 bbls per day, gas pressure had tailed off slightly
to 130 PSI and the API Gravity was holding at 29o.

 

 

 

 